Scheme Outline

Upgrade of the existing single two-lane route, which forms the main gateway into Nottingham from the South and the West Midlands. The route will be mostly dual two-lane with grade separated junctions, but reduces briefly to single four-lane approaching Clifton where land space is restricted. This last section will have at-grade roundabout junctions. Grade separated junctions will serve Ratcliffe Power Station, Barton-in-Fabis, and a potential Park and Ride site. The dualled section will terminate at Crusader Roundabout. Construction may now include construction or provision for a tram or rail line to East Midlands Airport.

Project Statistics

Cost
£90m
Finance
Highways Agency
Estimated completion of works
2008-2011
Length of works
8 miles

Progress

January 2007
Laing O'Rourke is appointed to develop the proposals.
March 2006
Local media reports that an announcement about the selected contractor is imminent, but a public inquiry will still be necessary.

More Information

Website
www.highways.gov.uk/roads/projects/4337.aspx

If you know more

If you have more details on this scheme - a correction to the information shown here or an update on the progress of works - please click here and share your knowledge.

With thanks to Tim Mollart, Andy Kettles, John Morgan, Chris Williams and Gerry McKenna for information on this page.