A19 New Tyne Crossing

You are here: Home - Futures - A19 New Tyne Crossing

Scheme Outline

Construction of a second two-lane tunnel alongside the existing one at Jarrow. The new tunnel would take all southbound traffic, with the existing one converted to take all northbound traffic. This project would provide continuous dual carriageway from the A1(M) at Dishforth via Middlesbrough and Newcastle to the A1 at Wide Open.

Project Statistics

Cost
£185m
Finance
Unknown
Estimated duration of works
2006-2009
Length of works
1 mile

Progress

July 2005
The Government approves construction of the second tunnel. Construction is due to start within a year.
June 2006
A legal challenge to the tunnel's construction by a member of Friends of the Earth has failed. The Tyne and Wear Passenger Transport Association will now look to appoint a concessionaire as soon as possible.

More Information

Website
www.newtynecrossing.info

If you know more

If you have more details on this scheme - a correction to the information shown here or an update on the progress of works - please click here and share your knowledge.

With thanks to Richard Kirkman and Gerry McKenna for information on this page.